Get a Large Generation Connection

Over 300kW Export

Large Generation

Exporting Over 300 kW

If you are considering or planning to build a solar farm, wind farm, grid scale battery or other form of generation that will be able to export electricity at over 300 kW capacity, talk to Unison as early as possible in your planning to help make your project a success. 

We’ll work with you through the phased process outlined below to assess your project’s feasibility and help you make informed investment decisions.

We will work together to:
  • explore the export capacity available

  • confirm the technical and safety requirements your project must meet,

  • identify any work needed on your site or our network

  • outline the likely costs, and

  • establish your project’s place in our connections pipeline.

Our process to get you approved

1

Pre-Application

Feasibility Stage

Come and talk to Unison before you commit to your project. We can give you some data and context to help you decide if your project has potential and if it is worth applying.

2

Initial Application

Feasibility Stage

When you’re ready to get clearer on the feasibility of your project, complete the initial application form and pay the application fee.

Initial Application Form

3

Indicative Decision

Feasibility Stage

We tell you if your application is feasible and give you information to help you decide if you want to proceed further. This includes your place in our pipeline, any further studies and network modifications needed, and estimated costs.

4

Studies & Results

Feasibility Stage

You have up to 12 months to complete the required technical studies with the help of your agent, consultant or Unison, and assess if the results meet Unison’s requirements.

5

Interim Application

Detailed Design Stage

You share your test results with your interim application. We assess the data, tell you if we can proceed, advise any conditions you will need to meet, and give you detailed costings for Unison’s part of the delivery.

Interim Application Form

6

Final Application

Detailed Design Stage

You make a final application confirming you accept and can meet the interim approval conditions. We confirm our final approval and costs, and your place in the connections pipeline.

Final Application Form

7

Negotiate Contract

Delivery Stage

We negotiate in good faith the technical and safety terms of your energy connection and any energy you export to our network once you’re connected. 

8

Network Upgrades

Delivery Stage

You apply separately to Unison to carry out the network upgrades identified in the interim and final decisions. We finalise the solution design and cost for these, and schedule the works once payment is received.

Learn more about getting a network upgrade

9

Build, Test, Connect

Delivery Stage

Your project team builds, tests and connects your generation system. Unison builds the network upgrades and delivers any modifications needed. Your retailer arranges import and export metering and updates the registry records. We go live.

Timeline to approval for a large generation system

The timeframes below are the maximum; most applications will be assessed and approved sooner. 

If your application is incomplete, we'll tell you what's missing, and the clock will restart once we have all the information we need. Ensuring you supply all the information up front is the fastest way to get your application assessed. 

If we need to come back to you for more information while we are assessing your application, the clock will pause again until we receive the information requested.  

We may need to extend the timeframe for our assessment where an application will require major network work, or Transpower involvement is needed. We will seek your agreement for any extension.


Large generation application timeframes

1) Unison notifies you of our indicative decision: within 8 weeks of receiving your  initial application
2) You complete your studies & submit results to Unison: within 12 months
3) Unison notifies you of our interim decision: 9-16 weeks from receipt of interim application
4) You submit a final application: within 18 weeks from notice of our interim decision
5) Unison notifies you of our final decision: 4-8 weeks from receipt of final application depending on size of project 
6) Negotiating export contract terms: within 6 weeks of you notifying us you want to negotiate

Total of Unison’s assessment and negotiation timeframes: 27-38 weeks*
* Excludes time for your own studies, your final application preparation, and any network upgrade works

NOTE: The above are maximums allowed under the electricity code. We expect most assessment times will be shorter and applications will be approved earlier.

Contact Details

Capacity queries: if you want to know more about capacity near your site

Connection Enquiries: if you want to talk to us about a potential connection

Phone: 0800 2 UNISON | 0800 2 86476 | e-mail: [email protected]