Considerations to make

Before you apply for a Large DG Connection

Before you apply

Let’s get it right first time

There are things you should consider and information to gather before you begin your application, to help the process run smoothly. We’ve laid out below the key technical and commercial information we think you might need to know. Please explore this content before beginning your application.


Let’s see what’s feasible

The first phase of the process is helping establish if an export connection is feasible for you and for our other network customers. You don’t need a final design or firm costs for your project to talk to us about a connection or to make your initial application. The first stage is about answering questions, not committing to outcomes.


Check out our capacity maps before you apply

Before you invest in any equipment or commit to a project, have a look at our network capacity in your location. This may influence the size of any generation system you can connect and how much electricity you can export from it.  This could in turn impact the feasibility of your project and connection. View our Capacity Maps


Talk to Unison early in the Process

We’d welcome you come and talk to us about your plans. It helps our own planning and gives us the opportunity to help you determine the feasibility of your project as early in your process as possible, and to contribute some ideas and suggestions that might help your final design, costings, timings.

Technical

Information on the technical aspects of connecting

Generation approvals for our network need to comply with some technical standards.  These are there to ensure that your generation system works for both you and for our other network customers, as well as protecting our staff and assets.  The standards cover things like safety, the quality and voltage of the power that is exported, and automatic shut down or disconnection of your system in the event of any defects at your or our end of the connection.

You can find more detail on our technical standards and a list of approved inverters.  We’d encourage you to talk to your installer about the ability of your system to meet these standards before applying.

We may require testing, inspection or certification that your system can meet all the standards as a condition or any interim approval of you application. We will detail the testing, studies or certification needed when we notify you of any initial or interim approval decision.

An export limit is the maximum amount of electricity your system can send into our network at any moment. It isn't a cap on how much your system generates, or on how much you use yourself. It only limits what goes out to Unison’s network.  

We set the limit for your connection, based on our connection standards and what the network in your area can take. Your installer configures your equipment to stay within that limit, usually through a setting on the inverter or a separate export control device. If no export control is fitted, we assess your system on its full capacity instead. So, limiting exports is often the simpler option.


It's measured across your whole site

If you have more than one inverter on your site, or you're adding to an existing system, we assess the combined total exporting into our network, not each inverter separately. Commercial systems usually run several inverters. Commercial systems often run several inverters. We assess the combined export across all of them. So, for example a site with eight 30 kW inverters is assessed on the total, not on 30 kW capacity of each one.


A limit is a ceiling, not a guarantee

Your limit is the most you may export. It isn't a promise that you'll always be able to export that much. In parts of our network where capacity is tight, exports may be reduced at times (see Congestion management for how and why that happens).


Keeping to your limit

We may verify your generation system's export capability, including by inspecting the installation; and your test or compliance documentation needs to show it's configured correctly. If you later want to change your export limit, you’ll need to submit a new application for that purpose, as you need our approval before changing your connection or your inverter's protection settings.

To ensure we can process and respond to your application for approval as quickly as possible, we’ve laid out below the key information to gather from your project team before completing your application to Unison.  

It’s also worth checking out our technical standards link here for further context or detail on the need for these data points:

What to gather

From Who

Maximum active power injected, in MW​

Your project engineer ​

The generation system design, including protection, synchronising and disconnection arrangements​

Your designer ​

Target energisation date for your project​

Your project team​

Whether Transpower is likely to be involved due to a need for any national grid connections 

Your project engineer

Investigative studies: what technical export studies you’ve already carried out and who will carry out any investigative studies that may be required by us for your application ​

Your project engineer​

A named technical contact we can deal with on the detail 

Also worth knowing before you start: this is a three-stage process (feasibility, detailed design, and delivery). Your first approval gives you a priority position in our published connections pipeline. This represents your claim on available network capacity. You will need to keep meeting approval application or connection milestones we agree with you to keep your position in the pipeline.  

Obtaining consents, land rights or completing investigative studies are likely to be amongst these milestones. While you don’t have to have obtained those at the time of making your first application, it’s worth knowing where you stand on them. You will need to reach all such milestones to keep your place in the pipeline queue. ​

We will give you an information pack to help you better understand what needs to be done for Unison to approve your generation connection. This pack should give you the information you need to decide whether you want to proceed or not, such as: what the network capacity and constraints are near your site, the impact your system could have on the safety and power quality of our systems, any modifications we will have to make to our network to accommodate your system, the approximate costs and timing to achieve that, obligations we or you may have to others (e.g. Transpower), and the impact planned or unplanned outages could have on your connection.

The pack will also detail any investigative studies you'll need to carry out to determine if your system could have any adverse effects on our network and systems. We’ll tell you who is qualified to conduct those studies. If we are one of those qualified parties, we’ll give you a cost estimate to carry out the studies.

If assessment of your initial application against our network standards demonstrates potential for your system to have adverse technical or safety effects on our network, we may ask you to conduct investigative studies of your system. We’ll tell you in the information pack we send you what these studies are, why they are needed, and who is qualified to carry them out. We may be one of the parties qualified, in which case we’ll give you an estimate of our costs. 

You will have up to 12 months to conduct any studies requested. Your application will effectively be placed on hold until we receive the results of your investigations, and you submit a final application to us for approval.

We may choose to send our personnel to observe any tests or inspections carried out by you or your project team as part of any investigative studies. We will invoice you for any reasonable costs we incur for observations.

Commercial

Information on the commercial aspects of connecting

When we approve your application, we'll set out any conditions your connection must meet, why we've applied them, and any charges involved. You need to formally accept those conditions to move to the next stage. If you disagree with a condition, there's a dispute process available, but you must notify us within 30 working days, and the clock keeps running.  

Conditions stay with your connection once you're operating, whether you're on our standard terms or a negotiated contract. If you later want to change something we've set as a condition, including your protection settings, you will need our approval first  

Conditions of approval are set at the interim stage, so you'll know what's required before you commit to the final application.

To approve medium to large generation systems connected to our network, we may need to undertake modifications to our network assets, configuration, or operations. Existing assets and systems may not be sufficient to enable larger generation systems, or the growth in these systems in parts of our network may exceed the technical requirements needed to accommodate them.  

When we assess applications for medium or large generation systems, we will determine if changes to our network are required. We will notify you of any modifications required when we give you our initial or interim approval decisions, and will give you approximate costs and timeframes to make these changes.  

If you can meet our approval conditions, wish to proceed with your project, and you submit a final application for your generation connection, please be aware you will also need to submit a separate application for the network modifications. This process will finalise the design, costs, scheduling, and delivery of the modifications. These works will need to be completed before your connection and exports can go live. 

If we approve your application, a standard set of connection terms applies automatically — there's nothing to sign. These terms cover aspects like safety, access, protection settings, who can switch what off and when, power quality and liability.  The generation terms are not a pricing contract for paying you for the electricity you export from your system (commonly referred to as a ‘buy back rate’).  You will need to enter into your own separate contract with an electricity retailer to receive any financial compensation for electricity you export.  

Standard contract terms will apply automatically for all approved applications.  These terms are mandatory for all approvals of fast-track applications with an inverter on Unison’s approved list.  Other applicants will have 30 business days medium from the date of our final approval to notify Unison.  You must reply within this timeframe, whether you are accepting the standard terms and all the conditions of our approval, or asking to negotiate a non-standard contract. If we do not hear from you, your approval will lapse and you will need to apply again.   

Together we will have 30 business days to conduct good faith negotiations to reach agreed contract terms. The standard terms under schedule 6.2 of the Electricity Participation Code will apply if we can’t agree on alternative terms.  The above notice and negotiation timeframes can in need be extended by mutual agreement.

Why congestion happens

Our network has a finite amount of room for electricity flowing in either direction. As more generation connects, and as demand grows and changes, some parts of our network will reach their limits. Where that happens, we manage it under our congestion management approach


What it means for you

Your approved export limit is the maximum you may send into our network. It isn't a guarantee that you'll be able to export that much at all times. In constrained parts of the network we may reduce or temporarily stop your export, and constraints can grow over time as more generation connects nearby. There is no payment for electricity you're unable to export.


We'll keep you informed

We'll make reasonable efforts to let you know before we interrupt your connection and work with you to limit the impact. Some situations, such as faults, emergencies, or safety risks, don't allow us to give full warning. Where an unplanned outage occurs, we'll do what we reasonably can to restore your connection and tell you how long we expect it to take.

Congestion isn't the only reason your export may be affected. Planned maintenance and construction, faults and storm damage, and safety issues can all interrupt your connection temporarily.


Check before you commit

Before you commit to a site, system or project we recommend you check out  our network capacity maps and congestion information. On these maps we publish the parts of our network that are congested now, and those we expect to become congested within the next 12 months. If you're choosing a site or sizing a system, look at those lists first.  They can affect the size of system you can connect or  amount of electricity you can export. They may also help point you toward locations where you can export more of what you generate.

If these maps suggest your project will be affected by existing or forecast congestion, talk to us early.  There may be options worth exploring before you settle on a point of connection.

We publish a monthly list of large generation and large load projects applying to connect to our network. It shows each project's size, type, location by zone substation or feeder, and where it has got to.  When we approve your initial application you'll be given a priority position in that pipeline. That position is your place in the queue for available network capacity.  You hold your position by meeting the delivery milestones we agree with you. Projects that consistently miss milestones can lose their place, and ultimately their approval.

Your project will appear in the published pipeline once it is approved. We don't publish your name or commercially sensitive details.

It is worth looking at the current pipeline before you commit to your connection.  It shows where capacity is already being taken up.

The following fees apply from 1 November 2024 for processing distributed generation applications for approval to install

Export Limit

Fee Type

Fee (excl GST)

Medium & Large Generation:

Over 10 kw

Application fee:  for administration and approval of installation

Generation above 10 kW and less than 100 kW

$770

Generation of 100 kW or above  and less than 1 MW

$1540

Generation of 1 MW and above

$7690

Excludes the costs of network modifications

The above costs relate to the approval of the generation installation and export contract only.  They do not cover the costs of any modifications Unison may have to make to its network or operations to enable your connection and export.  Approximate costs for this work if needed will be provided you in the information pack we provide with our indicative decision.  They will be finalized once you submit a separate application for the modifications and we complete our final design for the works themselves.

Contact Details

Capacity queries: if you want to know more about capacity near your site

Connection Enquiries: if you want to talk to us about a potential connection