Get a Medium Generation Connection

10-300kW Export

Medium Generation

Exporting between 10-300 kW

If you have or are planning to install a solar, battery, or generation system that can export between 10-300 kW of electricity to Unison’s network, follow the process below.

We'll complete an initial assessment of your plans and system and let you know.
  • If there is an opportunity to export to our network

  • What you need to do to demonstrate you can meet the technical and safety standards that protect our network and everyone connected to it

  • Any modifications we’ll need to make to our network to accommodate your connection

  • Information and costings to help you decide whether to proceed.

If you wish to proceed with your project after you've done your analysis, and you've confirmed you can meet all the requirements, you can make a final application. Once that’s approved, we can proceed with connecting your system.

Our process to get you approved

1

Pre-Application

Talk to your solar agent or electrician for advice about what's feasible. Check our technical standards, regulatory contract terms, and gather the information you’ll need to apply

2

Initial Application

Complete the online application form and pay the fee. Once paid, we'll review your application.

Initial Application Form

3

Feasibility Decision

We tell you if your application is feasible or not, give you information to help you decide if you want to proceed - including network capacity, likely constraints, approximate costs and any studies you'll need to commission to get final approval.

4

Studies & Results

You have up to 12 months to complete the required technical studies with the help of your agent, consultant or Unison, and assess if the results meet Unison’s requirements.

5

Final Application

You make a final application, pay the fee, and share your studies with us. We assess the results, tell you our final decision, and any conditions of our approval.

Final Application Form

6

Negotiate Contract

We negotiate in good faith the technical and safety terms of your energy connection and any energy you export to our network once you’re connected.

7

Network Upgrades

You apply separately to Unison to carry out the network upgrades identified in the interim and final decisions. We finalise the solution design and cost for these, and schedule the works once payment is received.

Learn more about getting a network upgrade

8

Build, Test, Connect

Your installer installs the equipment and ensures it is configured to comply with our standards. Your retailer arranges import and export metering and updates the registry records they share with networks like ours.

Timeline to approval for a medium generation system

The timeframes below are the maximum; most applications will be assessed and approved sooner. 

If your application is incomplete, we'll tell you what's missing, and the clock will restart once we have all the information we need. Ensuring you supply all the information up front is the fastest way to get your application assessed.

If we need to come back to you for more information while we are assessing your application, the clock will pause again until we receive the information requested.  

We may need to extend the timeframe for our assessment where an application will require major network work, or Transpower involvement is needed. We will seek your agreement for any extension. 


Medium generation application timeframes

1) Unison notifies you of any missing application data: within 1 week Missing data may delay our decision
2) Unison provides you with a detailed information pack: within 6 weeks
3) Unison notifies you of our feasibility decision: 8 weeks from receipt of your application
4) You complete your studies & submit results to Unison: up to 12 months 
5) Unison notifies you of our final decision: 9 weeks from receipt of your application
6) We negotiate export contract terms: within 6 weeks of you notifying us you want to negotiate

Total of Unison’s assessment and negotiation timeframes: 23 weeks*
* Assuming no missing data or studies required; excludes time for your own studies, your final application preparation, and any network upgrade works

NOTE: The above are maximums allowed under the electricity code. We expect most assessment times will be shorter and applications will be approved earlier.

Need more information?

Capacity queries:

if you want to know more about capacity near your site

Contact Us

if you want to talk to us about a potential connection