Considerations to make
Before you apply for a Medium DG Connection
Before you apply
Let’s get it right first time
There are things you should consider and information to gather before you begin your application, to help the process run smoothly. We’ve laid out below the key technical and commercial information we think you might need to know. Please explore this content before beginning your application.
Let’s see what’s feasible
The first phase of the process is helping establish if an export connection is feasible for you and for our other network customers. You don’t need a final design or firm costs for your project to talk to us about a connection or to make your initial application. The first stage is about answering questions, not committing to outcomes.
Check out our capacity maps before you apply
Before you invest in any equipment or commit to a project, have a look at our network capacity in your location. This may influence the size of any generation system you can connect and how much electricity you can export from it. This could in turn impact the feasibility of your project and connection. View our Capacity Maps
Speak with your installer or electrician
Your solar agent or installer, electrician or electrical consultant should have a good understanding of the technical requirements and feasibility of your system for a connection to Unison's network. We strongly recommend having a conversation with them before applying.
Technical
Information on the technical aspects of connecting
Generation approvals for our network need to comply with some technical standards. These are there to ensure that your generation system works for both you and for our other network customers, as well as protecting our staff and assets. The standards cover things like safety, the quality and voltage of the power that is exported, and automatic shut down or disconnection of your system in the event of any defects at your or our end of the connection.
You can find more detail on our technical standards and a list of approved inverters. We’d encourage you to talk to your installer about the ability of your system to meet these standards before applying.
We may require testing, inspection or certification that your system can meet all the standards as a condition or any interim approval of you application. We will detail the testing, studies or certification needed when we notify you of any initial or interim approval decision.
An export limit is the maximum amount of electricity your system can send into our network at any moment. It isn't a cap on how much your system generates, or on how much you use yourself. It only limits what goes out to Unison’s network.
We set the limit for your connection, based on our connection standards and what the network in your area can take. Your installer configures your equipment to stay within that limit, usually through a setting on the inverter or a separate export control device. If no export control is fitted, we assess your system on its full capacity instead. So, limiting exports is often the simpler option.
It's measured across your whole site
If you have more than one inverter on your site, or you're adding to an existing system, we assess the combined total exporting into our network, not each inverter separately. Commercial systems usually run several inverters. We assess the combined export across all of them. So, a site with eight 30 kW inverters is assessed on the total, not on 30 kW capacity of each one.
A limit is a ceiling, not a guarantee
Your limit is the most you may export. It isn't a promise that you'll always be able to export that much. In parts of our network where capacity is tight, exports may be reduced at times (see Congestion management for how and why that happens).
Keeping to your limit
We may verify your generation system's export capability, including by inspecting the installation; and your test or compliance documentation needs to show it's configured correctly. If you later want to change your export limit, you’ll need to submit a new application for that purpose, as you need our approval before changing your connection or your inverter's protection settings.
Most of the key information you will need to apply for a generation or export approval can be provided by your installer ordesigner. Below are some of the key data points to establish and collect before you start your application to Unison.
check out our technical standards for further context or detail on the need for these data points listed below.
What to gather | Who from |
Total maximum export power across all inverters combined | Your installer or designer |
The generation system design: number and model of inverters, protection and loss-of-mains arrangements, how the system connects and disconnects | Your designer |
Operating voltage and number of phases | Your installer or electrician |
Your site's existing electricity demand | Your bills or site records |
Expected export and consumption patterns, if known | Your installer or designer |
A named technical contact we can deal with on the detail |
|
Also worth knowing before you start: We'll come back within 30 working days with an information pack coveringnetwork capacity, likely constraints, approximate costs and any studies you'll need to commission. You don't have to dothose studies before applying, they shape your second-stage application, and you have 12 months to complete them.
We will give you an information pack to help you better understand what needs to be done for Unison to approve your generation connection. This pack should give you the information you need to decide whether you want to proceed or not, such as: what the network capacity and constraints are near your site, the impact your system could have on the safety and power quality of our systems, any modifications we will have to make to our network to accommodate your system, the approximate costs and timing to achieve that, obligations we or you may have to others (e.g. Transpower), and the impact planned or unplanned outages could have on your connection.
The pack will also detail any investigative studies you'll need to carry out to determine if your system could have any adverse effects on our network and systems. We’ll tell you who is qualified to conduct those studies. If we are one of those qualified parties, we’ll give you a cost estimate to carry out the studies.
If assessment of your initial application against our network standards demonstrates potential for your system to have adverse technical or safety effects on our network, we may ask you to conduct investigative studies of your system. We’ll tell you in the information pack we send you what these studies are, why they are needed, and who is qualified to carry them out. We may be one of the parties qualified, in which case we’ll give you an estimate of our costs.
You will have up to 12 months to conduct any studies requested. Your application will effectively be placed on hold until we receive the results of your investigations, and you submit a final application to us for approval.
We may choose to send our personnel to observe any tests or inspections carried out by you or your project team as part of any investigative studies. We will invoice you for any reasonable costs we incur for observations.
Commercial
Information on the commercial aspects of connecting
When we approve your application, we'll set out any conditions your connection must meet, why we've applied them, and any charges involved. You need to formally accept those conditions to move to the next stage. If you disagree with a condition, there's a dispute process available, but you must notify us within 30 working days, and the clock keeps running.
Conditions stay with your connection once you're operating, whether you're on our standard terms or a negotiated contract. If you later want to change something we've set as a condition, including your protection settings, you will need our approval first.
To approve medium to large generation systems connected to our network, we may need to undertake modifications to our network assets, configuration, or operations. Existing assets and systems may not be sufficient to enable larger generation systems, or the growth in these systems in parts of our network may exceed the technical requirements needed to accommodate them.
When we assess applications for medium or large generation systems, we will determine if changes to our network are required. We will notify you of any modifications required when we give you our initial or interim approval decisions, and will give you approximate costs and timeframes to make these changes.
If you can meet our approval conditions, wish to proceed with your project, and you submit a final application for your generation connection, please be aware you will also need to submit a separate application for the network modifications. This process will finalise the design, costs, scheduling, and delivery of the modifications. These works will need to be completed before your connection and exports can go live.
If we approve your application, a standard set of connection terms applies automatically — there's nothing to sign. These terms covers aspects like safety, access, protection settings, who can switch what off, and when, power quality and liability. The generation terms are not a pricing contract for paying you for the electricity you export from your system (commonly referred to as a ‘buy back rate’). You will need to enter into your own separate contract with an electricity retailer to receive any financial compensation for electricity you export.
Standard contract terms will apply automatically for all approved applications. These terms are mandatory for all approvals of fast-track applications with an inverter on Unison’s approved list. Other applicants will have (insert 10 business days small projects, 30 business days medium + large projects) from the date of our final approval to notify Unison. You must reply within this timeframe either way. Whether you are accepting the standard terms (and all the conditions of our approval) or asking to negotiate a non-standard contract. If we do not hear from you, your approval will lapse and you will need to apply again.
Together we will have 30 business days to conduct good faith negotiations to reach agreed contract terms. The standard terms under schedule 6.2 of the Electricity Participation Code will apply if we can’t agree alternative terms. The above notice and negotiation timeframes can in need be extended by mutual agreement between us.
Why congestion happens
Our network has a finite amount of room for electricity flowing in either direction. As more generation connects, and as demand grows and changes shape, some parts of our network will reach their limits. Where that happens, we manage it under our congestion management policy.
What it means for you
Your approved export limit is the maximum you may send into our network. It isn't a guarantee that you'll be able to export that much at all times. In constrained parts of the network we may reduce or temporarily stop your export, and constraints can grow over time as more generation connects nearby. There is no payment for electricity you're unable to export.
We'll tell you where we can
We'll make reasonable efforts to let you know before we interrupt your connection and to work with you to limit the impact. Some situations, such as faults, emergencies, or safety risks, don't allow for us to give full warning. Where an unplanned outage occurs we'll do what we reasonably can to restore your connection and tell you how long we expect it to take.
Congestion isn't the only reason your export may be affected. Planned maintenance and construction, faults and storm damage, and safety issues can all interrupt your connection temporarily.
Check before you commit
Before you commit to a site, system or project we recommend you check out our network capacity maps and congestion information. On these maps we publish the parts of our network that are congested now, and those we expect to become congested within the next 12 months. If you're choosing a site or sizing a system, look at those lists first. They can affect the size of system you can connect or amount of electricity you can export. They may also help point you toward locations where you can export more of what you generate.
The following fees apply from 1 November 2024 for processing distributed generation applications for approval to install
Export Limit | Fee Type | Fee (excl GST) |
Medium & Large Generation:Over 10 kw | Application fee: for administration and approval of installation | |
Generation above 10 kW and less than 100 kW | $770 | |
Generation of 100 kW or above and less than 1 MW | $1540 | |
Generation of 1 MW and above | $7690 | |
Excludes the costs of network modifications
The above costs relate to the approval of the generation installation and export contract only. They do not cover the costs of any modifications Unison may have to make to its network or operations to enable your connection and export. Approximate costs for this work if needed will be provided you in the information pack we provide with our indicative decision. They will be finalized once you submit a separate application for the modifications and we complete our final design for the works themselves.
Contact Details
Capacity queries: if you want to know more about capacity near your site
Connection Enquiries: if you want to talk to us about a potential connection
Phone: 0800 2 UNISON | 0800 2 86476 | e-mail: [email protected]