Tutukau Area Upgrade Project

Tutukau Area Upgrade Project

As part of our ongoing efforts to enhance the safety and reliability of your electricity, we will be replacing old poles and lines in the Tutukau area, including Te Kopia Rd, Mangamingi Rd, Pukemoremore Rd and State Highway 5. The current infrastructure is past its usable life and is due for replacement.

As part of this work, there will be several planned power outages in June and July. Look out for crews working in these areas:

When will the work happen?

We’ll have crews on site from early May through to the end of July 2026.

May: works commerce 

Watch out for additional vehicles/our trucks on the road – traffic management will be in place

June:
  • Number of Outages: 9
July:
  • Number of Outages: 2

*Note this plan is subject to change. For the latest outages visit our outages page.


How will this affect me?

  • Scheduled Power Outages: It’s estimated the project will require a series of outages, each lasting up to 7.5 hours.
  • Traffic Disruptions: You may notice additional vehicles and large trucks with poles and equipment on State Highway 5, Tutukau, Te Kopia, Mangamingi, Pukemoremore Rd. Please take care when driving through the area. 

We apologise for any inconvenience this may cause and appreciate your patience as we work to improve your power supply for the future. 


Stay Informed

You’ll be notified directly by your electricity retailer regarding the exact dates and times of the future planned outages. You can also check out outages web page and click on the future tab. We’ll also keep this webpage updated with important information throughout the duration of the project. 


Contact Us

If you have any questions about the project, feel free to contact our customer service team: